As oil production cuts boost confidence in the energy sector, Abu Dhabi National Oil Company (Adnoc) is pushing ahead with bullish plans to expand its refining capabilities, add value to its downstream products and form fresh partnerships with investors.

To achieve this, Adnoc is planning a capital expenditure of more than AED400bn ($109bn), approved by the Supreme Petroleum Council on 27 November, over the next five years.

As Abdulmunim Saif al-Kindy, head of Adnoc’s upstream directorate, notes: “If you look at Adnoc’s stated objectives, you get a clear view of where the money will be directed. We are going to raise production capacity and sustain it. We are also embarking on some unconventional work, and we are going downstream in both refining and petrochemicals.”

Abdulaziz Abdulla al-Hajri, head of the firm’s downstream directorate, continues: “More than 40 per cent of this expenditure will be in downstream. We are expanding our refining capacity by 60 per cent, and tripling our petrochemicals capacity from 4.5 million tonnes a year (t/y) today to 14.4 million t/y by 2025.”

Ruwais refinery

This capacity includes the plans for a new refinery at Ruwais that will be “targeted at 600,000 barrels a day (b/d), to expand our processing capacity to around 1.2 or 1.25 million b/d,” according to Al-Hajri.

Adnoc’s refining capacity currently stands at 922,000 b/d, out of which about 650,000 b/d is crude processing.

Abdulaziz Abdulla al-Hajri

Abdulaziz Abdulla al-Hajri

Adnoc’s petrochemical expansion efforts, meanwhile, include plans by Borouge, its joint venture with Borealis, to develop the Borouge 4 and polypropelene-5 (PP5) projects, which will raise capacity at the Ruwais complex for higher-margin plastics.

The Borouge 4 unit will increase the polyolefin capacity at Ruwais from 4.5 million t/y to more than 10 million t/y, making it the largest integrated polyolefin complex in the world.

“We are moving into the pre-feed [front-end engineering and design] and the selection of the processes and technologies,” says Al-Hajri. “We should start the feed by the middle of 2018.”

PP5 unit

Adnoc is in the tendering phase for its PP5 unit, which will use propylene from the existing Ruwais refinery to produce about 0.5 million t/y of polypropylene. The engineering, procurement and construction contract should be awarded by mid-2018.

The group also intends to develop 4 million t/y of aromatics capacity: “1.5 million t/y as part of the expansion of the current production of gasoline and other aromatics, and another roughly 3 million t/y from the new refinery,” says Al-Hajri.

The ultimate aim is for Ruwais to produce seven of the nine basic petrochemicals upon its completion.

According to the downstream director, these seven products support more than “90 per cent of all petrochemical and chemical manufacturing” in the world. “The integration opportunities make this project economically attractive to international investors, and we are already in discussions,” says Al-Hajri.

Strategic partners

Aside from Borouge 4, Adnoc’s partnerships include the planned development of a linear alkyl benzene complex with Spain’s Cepsa; and Elixier, an industrial gases joint venture with Germany’s Linde.

“Our main aim for the partnerships is smart growth and smart investments,” says Al-Hajri. “We are looking for partners who will help us add value, not only capital; partners who have the right technical knowledge and experience, and the right market access and security.

Adnoc is now engaged in discussions with several international companies interested in partnering with the firm on the development of the Ruwais refinery, in an open-ended equity arrangement that could see it offer up to a 40 per cent stake in Adnoc Refining.

“For the refinery, the best thing will be an integrated refinery and a single partner that will come in to expand the existing refinery with us and then add the new refinery as well,” says Al-Hajri.

Downstream investments

Adnoc also intends to look for opportunities to invest in downstream facilities in key target markets. “Our focus is and always will be the UAE,” he says. “But having said that, we will be evaluating opportunities to take our product downstream in key markets whether directly or indirectly – to be closer to our customer and find a captive outlet for our crudes.

“This will help us develop resilience and security against any changes in the market,” he says, adding that Adnoc International will be cooperating with other Abu Dhabi entities, such as Mubadala, to evaluate opportunities in countries including China and the emerging markets of southeast Asia.

Abdulmunim Saif al-Kindy

Abdulmunim Saif al-Kindy

The outstanding 60 per cent portion of the $109bn capital expenditure will be directed to Adnoc’s exploration and extractive capacity in its upstream business, where it is on track to expand its oil production capacity from 3 million b/d to 3.5 million b/d by the end of 2018.

Included in this target is an increase in production capacity at the Upper Zakum oil field, from just short of 750,000 b/d to about 1 million b/d.

Asked whether Adnoc is developing more capacity than it needs to hit its target of 3.5 million b/d, Al-Kindy says: “We are developing a capacity above our target – not really as sustainable production, but to cater for planned or unplanned disturbances or shutdowns.”

Energy security

The group is also refocusing on the exploitation of its untapped gas resources, both as a means of improving the UAE’s energy security, and as an opportunity in the context of falling subsidies.

As Al-Kindy notes: “We have always had an objective for self-sustenance of the UAE. But we also sized the conventional and unconventional opportunities, and developed a case for getting a fair price for our gas that, once achieved, would propel the gas developments from being commercially non-viable to being commercially viable.

“So the picture has changed from one of inability to meet the terms of the market to one where these can be developed and brought to the market at a commercial price.”
In terms of energy security, “we are aiming to be self-sufficient by around 2032,” he adds. 

Related Posts
Ten Minutes into the Future of Energy
CEO Mohamed al-Ramahi tells MEED he plans to increase Masdar’s international investments in renewable energy Visitors to the headquarters of Masdar (Abu Dhabi Future Energy Company) cannot fail to notice the bright, ...
READ MORE
Dubai awards construction contract for GCC’s first hydropower project
International consortium will build Hatta pumped-storage hydroelectric project Dubai Electricity & Water Authority (Dewa) has awarded a AED1.437bn ($391.2m) contract to a consortium of Austrian firms Strabag and Andritz and Turkey’s ...
READ MORE
Dubai prepares deep sewage tunnel tenders
Dubai Municipality is expected to tender construction work for the scheme during the first quarter of this year Dubai Municipality is preparing to issue tender documents for construction work for the ...
READ MORE
Work at Dubai Expo 2020 site keeps contractors busy
Construction work at the Expo 2020 site at Dubai South is steadily progressing The Expo 2020 site’s location on the outskirts of the city means most people living in Dubai do ...
READ MORE
Dubai’s switch from strategic to tactical infrastructure could bode well for PPP
Cuts to government infrastructure spending may not be as disappointing in the future Dubai’s budget for 2019 was a disappointing one for the projects sector, with 22.6 per cent less spending ...
READ MORE
Dubai ruler approves series of transport and public realm projects
The transit system will connect Dubai International Financial Centre, Downtown Dubai, Business Bay and City Walk Dubai’s Roads & Transport Authority (RTA) has received approval for a series of projects, including ...
READ MORE
Closing the healthcare talent gap 
This is article is the third in a series from the MEED-Mashreq Healthcare Business Leaders Forum held on 23 February in Dubai. The event saw leading industry experts gather to ...
READ MORE
CONSTRUCTION CLUB 3: Changing attitudes is key to construction moving forward
Highlights from the third MEED Mashreq Construction Club One consequence of the tougher trading conditions for construction companies in the GCC, is an increase in the number of projects being delayed, ...
READ MORE
The infrastructure financing challenge
Despite the appetite for a growing pipeline of infrastructure projects, significant barriers remain to the flow of global liquidity into the regional project market Across the Middle East and North Africa ...
READ MORE
What to expect project-wise in 2021
The region’s post Covid-19 projects market will be very different to the market before 2020 It has been a challenging few years for the Middle East and North Africa (Mena) projects ...
READ MORE
Ten Minutes into the Future of Energy
Dubai awards construction contract for GCC’s first hydropower
Dubai prepares deep sewage tunnel tenders
Work at Dubai Expo 2020 site keeps contractors
Dubai’s switch from strategic to tactical infrastructure could
Dubai ruler approves series of transport and public
Closing the healthcare talent gap 
CONSTRUCTION CLUB 3: Changing attitudes is key to
The infrastructure financing challenge
What to expect project-wise in 2021
27 December, 2017 | .By JOHN BAMBRIDGE